For a project being considered by a city in Alabama, the following cost data is available. Determine both the modified and conventional B/C ratios.
Initial cost = $10 million.
O & M cost / year = $450,000
Estimated annual benefit = $850,000
Life = 25 Years
Salvage value = $1 million
MARR = 6%
Correct Answer:
Verified
EUAC of initial cost...