The estimate providing the best accuracy for total project cost comes from (circle one) :
A) looking at the project as a whole
B) combining estimates from all the work packages
C) looking at the cost of similar, completed projects
D) the cost constraint specified by the customer.
Correct Answer:
Verified
Q1: The major problem with using traditional budgets
Q2: If the target cost is $235,000, which
Q3: If the actual cost turns to be
Q4: Which method relies on formulae and tables
Q5: Which method provides the least accuracy when
Q7: A contingency amount can be (circle one):
A)
Q8: Which of the following are potential ways
Q9: The project planning and estimating process (circle
Q10: Life cycle costs (circle all that are
Q11: Which of the following statements are true