Townsend Company budgeted 2,500 pounds of direct materials costing $32.00 per pound to make 1,250 units of product. The company actually used 2,400 pounds costing $35.50 per pound to make the 1,250 units. What is the direct materials efficiency variance?


A) $3,200 unfavorable
B) $3,550 favorable
C) $3,550 unfavorable
D) $3,200 favorable