A firm has found that the net present value of a project is equal to zero. The net present value was calculated using the firm's risk-adjusted discount rate of 15 percent. Based on this information, your conclusion is
A) the internal rate of return on the project is greater than 15 percent.
B) the internal rate of return on the project is equal to 15 percent.
C) the internal rate of return on the project is less than 15 percent.
D) the internal rate of return on the project may be greater than, equal to, or less than 15 percent depending on which method was used to adjust the firm's discount rate for risk.
Correct Answer:
Verified
Q3: A firm can borrow at an interest
Q4: The method of raising funds for capital
Q5: If the beta coefficient for a firm's
Q6: A firm is likely to select a
Q7: Which of the following is one of
Q9: If the net present value (NPV) method
Q10: Which of the following could be expected
Q11: A firm that is considering one independent
Q12: The profitability index for a project that
Q13: The internal rate of return on a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents