Seamus McTroid's Program, World Domination, Is in Phase Five

Question 163

Multiple Choice

Seamus McTroid's program, World Domination, is in phase five. Seamus wants to make archives of the information from the constituent projects. Which process should Seamus perform?


A) Administrative Closure
B) Close Program
C) Contract Closure
D) Component Closure

Correct Answer: