Caroline is managing a project at The Forrester Company. In the project charter she helped draft, it's noted that Systems A and B are assumed to be the only systems impacted; however, it comes to light several weeks later that System C is also impacted. Which statement is correct about this particular situation?
A) The constraints in the project charter will need to be adjusted by the Sponsor.
B) The assumptions in the statement of work will need to be adjusted by the Project Manager
C) The constraints and assumptions will need to be revisited by the Initiating Process Group and the overall project plan adjusted.
D) This project is a wash. Start from scratch.
Correct Answer:
Verified
Q1: Paralingual communication pertains to the way that
Q2: For which of the following should you
Q3: What is the BEST way to notify
Q5: A work authorization system is always required
Q6: Joe is a consultant. He is managing
Q7: Sherri Bobbins is formulating her scope management
Q8: The WBS is created by the project
Q9: What are the four options for dealing
Q10: By applying effective risk management techniques, what
Q11: What is Pareto's Law?
A)80% of the effects
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents