What Are Some Limitations of the PERT/critical Path Approach

Question 18

Multiple Choice

What are some limitations of the PERT/critical path approach?


A) It can place too much emphasis on the critical path.
B) Time estimates tend to be subjective.
C) Costs are not considered.
D) It can be time intensive to manage this way.
E) It is difficult to create reports.

Correct Answer: