Solved

Which of the Following Is Not Correct About Initial Phase

Question 11

Multiple Choice

Which of the following is not correct about initial phase of a project?


A) The cost associated at the beginning of the project is highest.
B) Stakeholders have maximum influence during this phase
C) The highest uncertainty is at this stage of the project.
D) All the above statements are correct.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents