Which of the following is not considered as a risk in project management?
A) Specification delays
B) Product competition
C) Testing
D) Staff turnover
Correct Answer:
Verified
Q7: Who has ultimate responsibility for project risk?
A)Steering
Q8: Who owns the Project Management Plan (PMP)?
A)The
Q9: A project is typically defined in terms
Q10: Which of these is not one of
Q11: Which of the following is NOT a
Q13: The process each manager follows during the
Q14: Quality planning is the process of developing
Q15: Which of the following is incorrect activity
Q16: Identify the sub-process of process improvement
A)Process introduction
B)Process
Q17: Choose an internal software quality from given
Unlock this Answer For Free Now!