If a rectangular pre-stressed beam of an effective span of 5 meters and carrying a total load 3840 kg/m, is designed by the load balancing method, the central dip of the parabolic tendon should be
A) 5 cm
B) 10 cm
C) 15 cm
D) 20 cm
Correct Answer:
Verified