Contract system is suitable for big projects
A) Right
B) Wrong
C) none
D) all
Correct Answer:
Verified
Q1: Which of the following is/are advantages of
Q2: Specialized work needs departmental execution
A)Right
B)Wrong
C)none
D)all
Q4: Departmental execution is suitable for small jobs
A)Right
B)Wrong
C)none
D)all
Q5: Which of the following is not essential
Q6: PERT requires
A)Single time estimate
B)Probable time estimate
C)Triple time
Q7: CPM requires
A)Single time estimate
B)Probable time estimate
C)Triple time
Q8: CPM is
A)Event oriented
B)Activity oriented
C)Mostly event oriented
D)Mostly activity
Q9: PERT is
A)Event oriented
B)Activity oriented
C)Mostly event oriented
D)Mostly activity
Q10: An activity is represented by
A)An arrow
B)Circle
C)Triangle
D)None of
Q11: An activity requires
A)Events
B)Time and resources
C)Resources
D)Energy
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents