The earliest method of project planning was
A) CPM
B) PERT
C) Bar chart
D) Mile stone chart
Correct Answer:
Verified
Q8: CPM is
A)Event oriented
B)Activity oriented
C)Mostly event oriented
D)Mostly activity
Q9: PERT is
A)Event oriented
B)Activity oriented
C)Mostly event oriented
D)Mostly activity
Q10: An activity is represented by
A)An arrow
B)Circle
C)Triangle
D)None of
Q11: An activity requires
A)Events
B)Time and resources
C)Resources
D)Energy
Q12: Actual performance of a task is known
Q14: A drawback of bar chart is that
A)All
Q15: A bar chart is drawn for
A)Time versus
Q16: Bar chart is also known as
A)Flow chart
B)Time
Q17: Bar chart is very popular because
A)It is
Q18: Bar chart is suitable for
A)Large project
B)Major work
C)Minor
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents