James Kirk is the project manager for a 5-year project, with a time tolerance of +3 months for the current stage. One of his team leaders, Monty Scott, reports a projected problem with a work package that is expected to take an extra 2 weeks. What action should Kirk take?
A) None
B) Produce an Exception Report.
C) Cancel the project.
D) Add an entry to the Risk Register.
Correct Answer:
Verified
Q1: Which of the following is a principle
Q2: Which of the following two roles sit
Q3: Which of the following documents is NOT
Q5: Which document defines the acceptance criteria and
Q6: Which of the following are valid threat
Q7: Which of the following is NOT a
Q8: Which role maintains the Quality Register?
A)Project Support
B)Project
Q9: Who is responsible for determining the Change
Q10: Which document is used to record issues
Q11: Which process allows non-PRINCE2 practices to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents