What is the labor budget for a project lasting six weeks with the following staffing?
• Principal ($200 per hour, two hours per week, six weeks)
• Professional Surveyor ($125 per hour, 20 hours per week, six weeks)
• Field Crew ($100 per hour, 40 hours per week, four weeks)
• Administrative Support ($25 per hour, 20 hours per week, six weeks)
A) $33,400
B) $36,000
C) $36,400
D) $44,400
Correct Answer:
Verified
Q9: Which of the following is an aliquot
Q10: Which type of business entity allows a
Q11: What type of business partnership entity is
Q12: What is the importance of the inclusion
Q13: What is the value of the following
Q15: Which of the following statements is NOT
Q16: The SW quarter of the NE quarter
Q17: Land descriptions are used to describe:
A)Personal property
B)Private
Q18: Which of the following are examples of
Q19: Fill in the blank: A _ is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents