Question 14

Multiple Choice

What is the labor budget for a project lasting six weeks with the following staffing?
• Principal ($200 per hour, two hours per week, six weeks)
• Professional Surveyor ($125 per hour, 20 hours per week, six weeks)
• Field Crew ($100 per hour, 40 hours per week, four weeks)
• Administrative Support ($25 per hour, 20 hours per week, six weeks)


A) $33,400
B) $36,000
C) $36,400
D) $44,400

Correct Answer: