Which role is responsible for realising the benefits?
A) Programme Manager
B) Senior Responsible Owner
C) Sponsoring Group
D) Business Change Manager
Correct Answer:
Verified
Q11: Which of the following is an output
Q12: Which of the following is NOT an
Q13: Which of these activities does "Delivering the
Q14: Which of these activities takes place as
Q15: In "Delivering the Capability," which role is
Q17: Which of the following is NOT an
Q18: Which of these is NOT an output
Q19: Who is responsible for confirming programme closure?
A)Senior
Q20: Which of the following is NOT one
Q21: Part of the project output to the