Solved

Which of the Following Should Not Be Part of the Programme

Question 102

Multiple Choice

Which of the following should not be part of the Programme Plan?


A) Project timescales, costs, outputs, and deliverables
B) Transition plans
C) Monitoring and control activities and performance targets
D) The detailed schedules for every project in the dossier

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents