The formula used to calculate the payback period for qualifying projects is ________.
A) Ct = ∑(Cd + Cᵢ)
B) Ct = PP/Bₐ
C) PP = ∑(Cd + Cᵢ)
D) PP = Ct/Bₐ
E) Bₐ = Cd + Cᵢ
Correct Answer:
Verified