Contracts -Joe the Plumber Contracts with Jane the Homeowner to Install

Question 45

Multiple Choice

Contracts
-Joe the plumber contracts with Jane the homeowner to install new sewer lines. The agreed upon price was $4,500. Halfway through the job, Joe told Jane that he had to change the price to $6,500. Jane refused to pay the additional $2,000. Joe refused to finish the work unless Jane paid. Jane reluctantly paid. Joe finished the work. Jane sued Joe for return of the $2,000. Who will win?


A) Jane will win based on the defense of fraud.
B) Jane will win because the modification of the contract terms was not supported by additional consideration from Joe.
C) Jane will lose because she agreed to the modification of the contract.
D) Jane will win based on the defense of physical duress.
E) Jane will win based on the defense of economic duress.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents