Oliver Owned a House on the Beach and Wanted to Add

Question 11

Multiple Choice

Oliver owned a house on the beach and wanted to add a deck so he could enjoy the ocean view. Oliver hired Carl Contractor to build the deck, and Carl started work two days later. Carl purchased $1,000 worth of wood and supplies before starting work on the deck. Five days later, before the project was completed, a hurricane totally destroyed the house and partially built deck. The contract is no longer in effect because it is impossible for Carl to complete it, but Carl may be able to recover damages for ______________.


A) Quantum meruit.
B) An impossible contract.
C) Consequential damages.
D) Incidental damages.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents