A Contractor Sends a Progress Billing to a City Requesting

Question 20

Short Answer

A contractor sends a progress billing to a city requesting payment of $4,000,000 for work done on a new fire station for the city. The city approves the payment less a 10 percent retainage but has not yet written a check to the contractor. What journal entry should be made in the city's Capital Projects Fund?
a.
 Expenditures-construction costs 4,000,000 Construction contracts payable 4,000,000\begin{array}{lrr}\text { Expenditures-construction costs } & 4,000,000 \\\quad \text { Construction contracts payable } && 4,000,000 \\\end{array}

b.
 Expenditures-construction costs 4,000,000 Retainage payable 400,000 Construction contracts payable 3,600,000\begin{array}{lrr}\text { Expenditures-construction costs } & 4,000,000 \\\quad \text { Retainage payable } &&400,000 \\\quad \text { Construction contracts payable } &&3,600,000 \\\end{array}

c.
 Capital assets-fire station 4,000,000 Retainage payable 400,000 Construction contracts payable 3,600,000\begin{array}{lrr}\text { Capital assets-fire station } &4,000,000 \\\quad \text { Retainage payable } &&400,000 \\\quad \text { Construction contracts payable } && 3,600,000 \\\end{array}

d.
 Expenditures-construction costs 3,600,000 Construction contracts payable 3,600,000\begin{array}{lrr}\text { Expenditures-construction costs } &3,600,000 \\\quad \text { Construction contracts payable } &&3,600,000\end{array}

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents