Liquidated damages that are unreasonably low will not be enforced __________.
A) as a matter of law
B) as a matter of fact
C) as despicable
D) as unconscionable
Correct Answer:
Verified
Q29: T.T. Inc. creates and sells hats. The
Q30: T.T. Inc. creates and sells hats. The
Q31: The UCC provides the buyer with an
Q32: A contractual remedy in which the court
Q33: A buyer may incur incidental and _
Q34: _ damages are damages that the parties
Q35: The parties _ add a liquidated damages
Q36: Liquidated damages clauses _ be enforced if
Q38: There are four critical dates that impact
Q39: T.T. Inc. creates and sells hats. The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents