In Spring 2017, Bava Construction Signed a Contract with the City

Question 34

Short Answer

In Spring 2017, Bava Construction signed a contract with the city of Springfield, to construct a new city hall for $200 million. Bava expects to construct the building within two years and incur expenses of $150 million, which means the company earns a $50 million profit on the contract. The city of Springfield paid $50 million when the contract was signed, $100 million within the next six months, and the final $50 million exactly one year from the signing of the contract. Bava incurred $60 million in costs during 2017 and rest in 2018 to complete the contract on time.
Using the cost-to-cost method how much revenue should Bava recognize in 2017? What profit from the Springfield contract, will the company report each year?

Correct Answer:

verifed

Verified

According to the cost-to-cost method, Ba...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents