Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true? A) None of the tasks have slack. B) Task O has 3 days of slack. C) Task L has 4 days of slack. D) Task D has 2 days of slack. E) Task L has 3 days of slack.
-Based on the information, which of the following statements is true?


A) None of the tasks have slack.
B) Task O has 3 days of slack.
C) Task L has 4 days of slack.
D) Task D has 2 days of slack.
E) Task L has 3 days of slack.

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents