Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.
-If the container size were 15 and there were 10 containers, what would be the new required round-trip time, all else being constant?
A) 4 hours
B) 5 hours
C) 6 hours
D) 7 hours
E) 8 hours
Correct Answer:
Verified
Q34: Lady Bug Machineries uses a lean production
Q35: Lady Bug Machineries uses a lean production
Q36: Lady Bug Machineries uses a lean production
Q37: Lady Bug Machineries uses a lean production
Q38: Lady Bug Machineries uses a lean production
Q40: Lady Bug Machineries uses a lean production
Q41: The Frankenmuth Fasteners Co. was implementing lean
Q42: The Frankenmuth Fasteners Co. was implementing lean
Q43: The Frankenmuth Fasteners Co. was implementing lean
Q44: The Frankenmuth Fasteners Co. was implementing lean
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents