The Frankenmuth Fasteners Co

Question 45

Multiple Choice

The Frankenmuth Fasteners Co. was implementing lean throughout their shop floor and needed to determine the number of containers at several of their work centers. In one such work center, the demand was 200 parts per hour, and the containers they used for this part held 50 parts. It normally takes 6 hours for a full container to make a circuit through the work cell and back to its input side, and they desired to carry 12% safety stock in the system.
-Based on the required safety stock of zero and the number of containers computed in Question 41, what would be the new required round-trip time, all else being constant?


A) 7 hours
B) 6.03 hours
C) 6.75 hours
D) 7.8 hours
E) 6 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents