The Frankenmuth Fasteners Co. was implementing lean throughout their shop floor and needed to determine the number of containers at several of their work centers. In one such work center, the demand was 200 parts per hour, and the containers they used for this part held 50 parts. It normally takes 6 hours for a full container to make a circuit through the work cell and back to its input side, and they desired to carry 12% safety stock in the system.
-Based on the required safety stock of zero and the number of containers computed in Question 41, what would be the new required round-trip time, all else being constant?
A) 7 hours
B) 6.03 hours
C) 6.75 hours
D) 7.8 hours
E) 6 hours
Correct Answer:
Verified
Q40: Lady Bug Machineries uses a lean production
Q41: The Frankenmuth Fasteners Co. was implementing lean
Q42: The Frankenmuth Fasteners Co. was implementing lean
Q43: The Frankenmuth Fasteners Co. was implementing lean
Q44: The Frankenmuth Fasteners Co. was implementing lean
Q46: The Frankenmuth Fasteners Co. was implementing lean
Q47: The Frankenmuth Fasteners Co. was implementing lean
Q48: The Frankenmuth Fasteners Co. was implementing lean
Q49: The Frankenmuth Fasteners Co. was implementing lean
Q50: The Frankenmuth Fasteners Co. was implementing lean
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents