Assume that all of the jobs below arrived at the same time. Also assume that transfer times are zero and jobs cannot be split
-Using a Gantt chart and the processing order as per the critical ratio (CR) rule, determine the average tardiness.
A) 0.8 hrs
B) 6.6 hs
C) 11.6 hrs
D) 15 hrs
E) 18 hrs
Correct Answer:
Verified