The process design team at a medical device manufacturer has broken an assembly process into 8 basic steps, each with a required time and predecessor, as shown in the table. There are 8 productive hours available in a day, and the manufacturer wishes to produce 400 units.
-Operations managers and process engineers design a line that contains 7 stations. What is the percentage of idle time?
A) 29.56%
B) 19.80%
C) 37.60%
D) 14.30%
E) Need more information to answer the question
Correct Answer:
Verified
Q58: Assume a facility is open 8 hours
Q59: Assume a facility is open 8 hours
Q60: Assume a facility is open 8 hours
Q61: The process design team at a medical
Q62: The process design team at a medical
Q64: The process design team at a contract
Q65: The process design team at a contract
Q66: The process design team at a contract
Q67: The process design team at a contract
Q68: A tier-two supplier needs to produce 300
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents