The Process Design Team at a Medical Device Manufacturer Has

Question 63

Multiple Choice

The process design team at a medical device manufacturer has broken an assembly process into 8 basic steps, each with a required time and predecessor, as shown in the table. There are 8 productive hours available in a day, and the manufacturer wishes to produce 400 units.
The process design team at a medical device manufacturer has broken an assembly process into 8 basic steps, each with a required time and predecessor, as shown in the table. There are 8 productive hours available in a day, and the manufacturer wishes to produce 400 units.    -Operations managers and process engineers design a line that contains 7 stations. What is the percentage of idle time? A) 29.56% B) 19.80% C) 37.60% D) 14.30% E) Need more information to answer the question
-Operations managers and process engineers design a line that contains 7 stations. What is the percentage of idle time?


A) 29.56%
B) 19.80%
C) 37.60%
D) 14.30%
E) Need more information to answer the question

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents