A car repair shop has two hoists where cars can be lifted for repair work. Currently customers come in at the rate of 4 per hour and are processed at a similar rate. On average 8 cars are waiting to be processed, 4 needing routine repairs and 4 needing major repairs. People are served on a first come first serve basis.
(a) How long do customers wait on average before being processed?
(b) The repair shop owner feels that he is losing many customers needing routine repair because of the long wait. He dedicates one hoist for routine repair and one for major repairs. A study indicates that routine repairs are processed at the rate of 3 per hour and major repairs at the rate of 1 per hour. There are now 5 people waiting on average for routine repairs and 3 waiting on average for major repairs. How long does each type of customer now wait before being served?
(c) With the new system, what is the average waiting time over all customers?
Correct Answer:
Verified
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents