Solved

Bretts Construction Company Had a Contract Starting April 2008, to Construct

Question 42

Multiple Choice

Bretts Construction Company had a contract starting April 2008, to construct a $6,000,000 building that is expected to be completed in September 2010, at an estimated cost of $5,500,000. At the end of 2008, the costs to date were $2,530,000 and the estimated total costs to complete had not changed. The progress billings during 2008 were $1,200,000 and the cash collected during 2008 was $800,000. Bretts uses the percentage-of-completion method.
-At December 31, 2008, Bretts would report Construction in Process in the amount of


A) $230,000.
B) $2,530,000.
C) $2,760,000.
D) $2,360,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents