The Glass Shop, a manufacturer of large windows, is experiencing a bottleneck in its plant. Setup time at one of its workstations has been identified as the culprit. A manager has proposed a plan to reduce setup time at a cost of $72,000. The change will result in 8,000 additional windows. The selling price per window is $18, direct labour costs are $3 per window, and the cost of direct materials is $5 per window. Assume all units produced can be sold. The change will result in an increase in the throughput contribution of
A) $104,000.
B) $80,000.
C) $32,000.
D) $8,000.
E) $120,000.
Correct Answer:
Verified
Q37: The firm has a $2,000 maintenance contract
Q38: A client in another province needs immediate
Q39: A client in another province needs immediate
Q40: Which of the following is NOT a
Q41: Which of the following sets of sentences
Q43: Palmateer Industries makes an electronic component in
Q44: Brix, Inc., prepares frozen food for fast-food
Q45: Aunt Lydia's Cookies, Inc., prepares frozen gourmet
Q46: Electrical Engineering Equipment Ltd. purchased a machine
Q47: Pat, a Pizzeria manager, replaced the convection
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents