Which of the following best defines learning curve?
A) Repetition is inversely related to productivity.
B) Productivity increases as repetitions increase.
C) Worker productivity is a constant.
D) Productivity decreases as the size of a project increases.
E) None of the above
Correct Answer:
Verified