Which listed procedure should be followed to accomplish a change in work that must be executed immediately?
A) The designer should immediately provide supplemental instructions to the contractor.
B) The owner should immediately request a proposal, then promptly negotiate the necessary change.
C) A change directive should be provided to the contractor by the construction manager or owner.
D) The contractor should anticipate the need for the change, do the work, then request appropriate payment.
E) None of the above
Correct Answer:
Verified
Q1: Match the orrect description with the communication
Q2: Match the orrect description with the communication
Q3: Match the orrect description with the communication
Q4: Match the orrect description with the communication
Q5: Match the orrect description with the communication
Q6: An application for payment submitted by the
Q7: On large projects owner retainage, typically 10
Q9: Contractors should expect an extension of time,
Q10: Which of the listed methods of dispute
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents