Use the following information to answer questions
Tennis Pro's standard assembly time per tennis racket is 0.40 hours at a standard cost of $10 per labor hour. During January 2010, Tennis Pro produced 5,000 tennis rackets in 2,300 labor hours at a cost of $9.50 per labor hour. Tennis Pro had budgeted to produce 4,800 tennis rackets in January 2010.
-What is Tennis Pro's labor efficiency variance?
A) $3,800 unfavorable
B) $2,850 unfavorable
C) $2,850 favorable
D) $3,000 favorable
E) $3,000 unfavorable
Correct Answer:
Verified
Q40: Use the following information to answer questions
Q41: Use the following information to answer questions
Q42: Use the following information to answer questions
Q43: Use the following information to answer questions
Q44: Use the following information to answer questions
Q46: Use the following information to answer questions
Q47: Use the following information to answer questions
Q48: The standard overhead cost is equal to
Q49: An extremely large favorable material price variance
Q50: Purchasing higher quality material than normally purchased
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents