An owner urgently wants to select a contractor. However, the project details have not been finalized. Therefore, the owner wants to have a few contractors give rough price estimates, and then enter into negotiations with one or more of them. What type of delivery system is most appropriate for this situation?
A) request for qualifications
B) invitation to tender
C) request for quotation
D) request for standing offer
Correct Answer:
Verified
Q1: A request for quotation may be used
Q2: Standing offers are typically open for a
Q3: What consequences result from tender documents that
Q4: If an owner wants to negotiate with
Q5: In which of the following project delivery
Q7: A large private developer anticipates a complicated
Q8: Which of the following is good practice
Q9: Which of the following models for project
Q10: If a call for tenders specifically requires
Q11: An owner wants to implement a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents