Which of the Following Is False Regarding the Issue of Time

Question 4

Multiple Choice

Which of the following is false regarding the issue of time under a contract?


A) typically, time is of the essence for both parties
B) since the contractor will be liable for late completion, only he need be concerned with the feasibility of the construction schedule
C) when scheduling, minor tasks should be given as much consideration as major tasks
D) all of the above

Correct Answer:

verifed

Verified