Contractor A employed two subcontractors, B and C. The total holdback retained by A is $100. B and C file liens for $60 and $240 respectively. Assuming there are no other liens on the project, the holdback amount is correct and the liens are proven, how much will C recover from the holdback?
A) $80
B) $100
C) $240
D) none of the above