Comprehensive - Chapter 16 & 17
Maxym Yattselev, the managerial accountant has been asked by the Keepit Cool Ceiling Fan Company president to prepare an analysis of the effectiveness of the new management team. They manufacture paper fans.
2005 standards
Budget
Direct materials - 4 parts @ $2 per part
Direct labor - one half hour (0.5) @ $10 per hour
Variable overhead 2 machine hours @ $3 per hour
Fixed overhead $900,000
Estimated production 100,000
Actual results 2005
Direct materials 585,000 parts at a total cost of $ 1,462,500 were purchased and used
Direct labor 51,000 hours at a cost of $561,000
Variable overhead 240,000 machine hours at a cost of $840,000
Fixed overhead $870,000
Actual production 130,000 fans
Required:
(1) Compute the direct material and direct labor budget variances
(2) Compute the variable and fixed overhead variances
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q83: Discuss the meaning of the fixed overhead
Q84: The company closes all variances to cost
Q85: At the beginning of the year, the
Q86: Briefly discuss how standard cost variances
Q87: Garcia and Company has just finished
Q89: Briefly describe how a standard-cost
Q90: Tillery Company's production V.P. has a problem.
Q91: Reed Company uses a standard costing system
Q92: Cucto Company uses machine hours to allocate
Q93: Ms. Garcia, the controller for Romine Inc.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents