A first to file, first in right state will:
A) Give mechanics priorities back to the time construction began.
B) Give general contractors priority over subcontractors.
C) Give mechanics priorities according to the time each individual project is begun.
D) Give mechanics priorities according to their time of lien filing.
Correct Answer:
Verified
Q35: In the majority of states, the filing
Q36: A purchaser is subject to liens only
Q37: Stop-notice statutes are unconstitutional.
Q38: Stop-notice payments are given to general contractors.
Q39: Which of the following is an example
Q41: Which of the following does not affect
Q42: A termination of a lien occurs in
Q43: When there are more lien claims than
Q44: Which of the following parties is not
Q45: A lien waiver:
A) Is given by a
Unlock this Answer For Free Now!