Question 90

Multiple Choice

Which of the following is the fourth primary step in designing a PERT network?


A) determining the time needed for the completion of each activity or event
B) designing a PERT network reflecting all the information needed
C) identifying the sequence of events and activities requiring the longest period of time to complete
D) listing the sequence in which the activities/events have to be performed
E) listing all the activities or events that must be accomplished for the project

Correct Answer: