Multiple Choice


A print shop has contracted to print a number of jobs within 24 hours.Any jobs not completely printed within this time will result in a penalty,as shown in the table above.However too many jobs have been accepted,and not all can be printed.Which jobs should be printed in the next 24 hours?
A) Job D and Job A
B) Job C and Job B
C) Job C, Job B, and Job E
D) Job D, Job A, and Job E
E) Job C, Job D, and Job E
Correct Answer:
Verified