The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6.
a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q40: Describe the differences between a Gantt chart
Q113: Consider the network described in the
Q115: Briefly discuss what is meant by critical
Q116: A partially solved PERT problem is
Q117: Three critical path activities are candidates
Q118: A network consists of the following
Q119: What are the advantages of using PERT
Q121: Given the critical path below, calculate
Q122: Pirmin's Bike Shop is behind on
Q123: Consider the network presented in the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents