A contractor builds large ships for the Department of Defense. A recent contract called for 12 amphibious landing platforms. It was originally estimated that the first of these would cost $1 billion and that 80 percent learning would be appropriate. In fact, the first ship cost $1.6 billion and the second $1.12 billion. What is the revised learning rate?
What will be the total cost of the twelve ships?
Is it higher or lower than the original estimates?
If the defense department cuts the contract from 12 ships to 9, what happens to the average cost per ship?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q42: Explain how learning curves might be applied
Q49: Explain how learning curves might be applied
Q81: A company is preparing a bid on
Q95: A certain product under development took 200
Q96: Your firm has expertise with a special
Q97: In the Learning-Curve Coefficients table for 70
Q103: A product was priced assuming an 80%
Q104: A small manufacturer builds wooden pleasure boats
Q105: Using the arithmetic concept determine how long
Q106: The seventh unit of production took 63.423
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents