A Contractor Builds Large Ships for the Department of Defense

Question 100

Essay

A contractor builds large ships for the Department of Defense. A recent contract called for 12 amphibious landing platforms. It was originally estimated that the first of these would cost $1 billion and that 80 percent learning would be appropriate. In fact, the first ship cost $1.6 billion and the second $1.12 billion. What is the revised learning rate?
What will be the total cost of the twelve ships?
Is it higher or lower than the original estimates?
If the defense department cuts the contract from 12 ships to 9, what happens to the average cost per ship?

Correct Answer:

verifed

Verified

The original estimates called for $1 bil...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents