Your Company Is Making Experimental Turbochargers for a New Design

Question 88

Essay

Your company is making experimental turbochargers for a new design of high-powered farm tractors. The production schedule for these new components is contained in the table below.
 Month  Turbochargers 1426374855\begin{array} { | c | c | } \hline \text { Month } & \text { Turbochargers } \\\hline 1 & 4 \\\hline 2 & 6 \\\hline 3 & 7 \\\hline 4 & 8 \\\hline 5 & 5 \\\hline\end{array}
The first turbocharger, a trial unit, took 900 hours to produce. Based on your experience with similar products, the learning factor is 85%. You have 20 employees, and each employee works 160 hours per month. How many hours will be required in each month?
In which month(s) will overtime be required to meet the production schedule?

Correct Answer:

verifed

Verified

Use the Total time column of the 85% sec...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents