Takt time is
A) the total work time available divided by units required by the consumer
B) the units required divided by workers required
C) a fictional time increment similar to a therblig
D) the same thing as cycle time in a process layout
E) an important consideration in balancing an assembly line
Correct Answer:
Verified
Q68: Which of the following requires an information
Q69: ASRS stands for
A) automated storage and retrieval
Q69: A process layout problem consists of 4
Q70: The assumption of stability of demand is
Q73: Solving a load-distance problem for a process-oriented
Q74: Which layout type assumes an adequate volume
Q75: Which of the following does not support
Q76: Which of the following is not an
Q94: Balancing a work cell is done:
A)before the
Q199: Ambient conditions; spatial layout and functionality; and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents