Four hundred and eighty minutes of production time are available per day.The schedule calls for the production of 80 units per day.Each unit of the product requires 30 minutes of work.What is the theoretical minimum number of workstations?
A) 2
B) 3
C) 4
D) 5
E) 6
Correct Answer:
Verified
Q120: Four hundred and eighty minutes of production
Q126: A firm operates a flow shop building
Q274: Heuristics are problem-solving procedures that mathematically optimize
Q286: Which of the following is a common
Q292: In assembly-line balancing, cycle time (the ratio
Q294: The central problem in product-oriented layout planning
Q307: Assembly line balancing has just been used
Q308: _ is the maximum time that the
Q317: A(n) _ line is a machine-paced product-oriented
Q319: What are the advantages and disadvantages of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents