A task involves positioning two metal parts with a rubber gasket sandwiched between them, inserting two bolts into predrilled holes, threading a nut onto each bolt, and tightening each bolt with a pneumatic wrench. In a preliminary study, the manager observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
a. What is the average observed time for this task?
b. What is the normal time for this task if the employee worked at a 10% slower pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 8% constant and 6% variable?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q144: What are predetermined time standards?
Q180: What are the disadvantages of work sampling?
Q181: A manufacturing plant is trying to determine
Q182: The data in the following table
Q183: The data in the following table
Q185: What is the required sample size to
Q186: An operation in a television factory has
Q187: A Methods and Measurements Analyst needs
Q188: Suppose that an analyst takes 50 samples
Q189: A manufacturing plant assembly line job has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents