A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
If the company wants the output rate to be equal to demand, what would be the efficiency of this line with the theoretical minimum number of workstations?
A) 100 percent
B) 92.5 percent
C) 75 percent
D) 87.5 percent
E) 90 percent
Correct Answer:
Verified
Q109: The maker of the world-famous Chocolate Chip
Q110: QRS Corp. is designing a product layout
Q111: A company is designing a product layout
Q112: The maker of the world-famous Chocolate Chip
Q113: QRS Corp. is designing a product layout
Q115: A company needs to locate three departments
Q116: A company needs to rebalance a product
Q117: The maker of the world-famous Chocolate Chip
Q118: A company needs to rebalance a product
Q119: QRS Corp. is designing a product layout
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents