QRS Corp Is Designing a Product Layout for a New Product

Question 107

Multiple Choice
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: 
For output to equal forecasted demand, what is the theoretical minimum number of workstations needed?
A) 1 
B) 3 
C) 3.75 
D) 4 
E) 5

QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:   For output to equal forecasted demand, what is the theoretical minimum number of workstations needed? A)  1 B)  3 C)  3.75 D)  4 E)  5
For output to equal forecasted demand, what is the theoretical minimum number of workstations needed?


A)  1
B)  3
C)  3.75
D)  4
E)  5

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents