A job has an observed cycle time of four minutes, a performance rating of 80 percent, and an allowance that is 20 percent of job time. Normal time for the job in minutes is:
A) 3.20.
B) 3.84.
C) 4.00.
D) 4.80.
E) 5.00.
Correct Answer:
Verified
Q77: A behavioral approach to job design which
Q83: In work sampling, how will increasing the
Q121: The chart used to focus on busy
Q122: Which of the following most closely describes
Q130: A simo chart includes:
A)delay.
B)storage.
C)transportation.
D)left/right hand movements.
E)inspection.
Q140: The chart used to review the overall
Q143: A technique for estimating the proportion of
Q149: In work sampling, observations should be taken:
A)at
Q150: Time standards derived from a firm's historical
Q177: A disadvantage of teams is:
A)higher quality.
B)higher productivity.
C)greater
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents