Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:
If Eva uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?
A) 3 hours
B) 5 hours
C) 7 hours
D) 7.2 hours
E) 8 hours
Correct Answer:
Verified